The plant was the winner of the fifth installment of CRE 4 “photovoltaic installations on buildings” calls for tenders and benefits from a 20-year contract for the sale of the electricity produced.
The new Angers rink replaces the obsolete Haras rink. It is right next to a tram station in the heart of a new neighborhood of the city: “ZAC Angers St Serge”. This flagship project reinforces the attractiveness of the area.
The total roof area is 10,000 m2. Construction of the building took place between July 2017 and August 2019. Installation of the modules was completed in November 2019.
The solar power plant fits naturally into the overall approach to limiting the environmental impact of the ice rink.
Result of an investment of € 250K, the project with 766 GCLSI modules represents a total power of 249 kWp and will produce, according to estimates, 252 MWh / year which will be injected into the Enedis public grid.
ALTER Energies a souhaité impliquer les Angevins via une collecte citoyenne pour participer au financement de ses deux projets de centrales solaires (Angers et Beaucouzé). Lancé sur le site Lendopolis la “cagnotte” a réuni 121 personnes pour un montant total de 50000€. Chaque participant a versé en moyenne 413€ sous forme d’un prêt sur 4ans rémunéré à hauteur de 3,5% par an.
Sources of figures: ALTER et LENDOPOLIS
0.21 MWp power installed
0.3 GWh production / year
540 modules
📍 Murviel les béziers, Hérault (34) France
2.5 MWp power installed
2.880 GWh production / year
5 670 modules
📍 Saint-Cyr-sur-Loire (37)
0.250 MWc power installed
0.461 GWh production / year
558 modules
📍 Marseille, Bouches-du-Rhône (13) France